LYNCHBURG, Va. – Highway work requiring road/lane/structure closures is planned;

however, work may be delayed/canceled due to weather or other issues. Items in

italics contain new/updated information. For up-to-date information, call 511 or visit

www.511Virginia.org.

District-wide activities:

Crews will perform various activities throughout the district to include, but are not limited

to bridge & guardrail maintenance, brush/tree/limb cutting, pothole/surface/shoulder work,

surface treatment/paving operations, work orders, mowing, boom axing, drainage repairs/

work and roadside cleanup.

Work at specific locations:

Amherst County:

Route 29 & Route 151 (Patrick Henry Hwy.) – Construction of a Restricted Crossing U-

Turn, storm drainage, advanced warning flashers, traffic lighting. Work to begin on

March 1. Use caution and watch for changes in the traffic pattern during construction.

Estimated completion November 2024.

Please note district-wide activities above.

Appomattox County:

Route 131 (Old Courthouse Rd.) from Route 460 BUS (Confederate Blvd.) to Route 460

Bypass (Richmond Highway) – Route 131 Reconstruction. Traffic shift was put in place

on Wednesday, December 13, 2023. Lane closures expected. Use caution. Estimated

completion January, 2025.

Please note district-wide activities above.

Bedford County:

Please note district-wide activities above.

Buckingham County:

Please note district-wide activities above.Charlotte County:

Route 15 (Farmville Highway) at Route 15/360 BUS (Four Locust Highway) – Roundabout

project. Change in traffic pattern now in place allowing two-way movement along Route

15/360 BUS (Four Locust Highway) and a stop condition for Rte. 15 (Farmville Highway)

southbound traffic. The on-ramps from Route 15 to the Route 15/360 (Kings Highway) and

the off-ramp from Route 15/360 (Kings Highway) to Route 15 are closed to traffic.

Message boards and detour signage will alert motorists to the change and direct traffic

along the detour. Estimated overall project completion October 2024.

Route 701 (Thorntons Mill Road) – Debris removal. Route 701 (Thorntons Mill Road) is

closed from Route 691 (Tower Road) to Route 615 (Rolling Hill Road) due to debris

removal. A detour with signs is in place. Estimated completion March 22, 2024.

Please note district-wide activities above.

Cumberland County:

Route 45 (Cartersville Rd.) at Route 690 (Columbia Rd.) – Roundabout Project. Shoulder

and lane closures expected. Use caution. Estimated completion November 2024.

Please note district-wide activities above.

Halifax County:

Route 501 (L P Bailey Memorial Highway) at Route 628 (Chestnut Road) – Intersection

improvement project. Shoulder and lane closures began on February 5th. Use caution.

Estimated completion December 2024.

Route 610 (Crystal Hill Rd.) – Bridge Replacement. Route 610 (Crystal Hill Road) is closed

to through traffic from Route 641 (Lower Liberty Rd.) to Route 626 (Howard P. Anderson

Road). Estimated completion March 29, 2024.

Please note district-wide activities above.

Lynchburg:

Please note district-wide activities above.

Nelson County:

Route 29, between Route 6 (River Rd.) and Route 718 (Mountain Cove Rd.) – Shoulder

widening, rumble strip installation, guardrail installation. Work to begin March 4 and cause

alternating lane closures. Estimated completion January 2025.

Route 674 (Jenny’s Creek Rd.) – Emergency road repairs. Motorists should expect delays

on Route 674 (Jenny’s Creek Rd.) in Nelson County due to emergency road repairs. A

culvert underneath the roadway has collapsed. Expected completion March 6, 2024. A

detour is in place, utilizing Route 56 (Tye Brook Hwy.) and Route 151.

Route 60 over James River – Bridge deck replacement. Lane closures and changes in

traffic patterns in effect. Traffic is utilizing the other side of the bridge to cross. Est. comp.

end of July 2024.

Please note district-wide activities above.

Pittsylvania County:

Please note district-wide activities above.Prince Edward County:

Route 665 (Worsham Road) – Bridge Replacement. Route 665 (Worsham Road) will be closed

to through traffic from Route 15 (Farmville Road) to the intersection of Route 630 (Redd Shop

Road) from 1/29/2024 – 5/31/2024. A detour with signs will be in effect, using Route 15 to

Route 628 (Granite Falls Blvd.) to Route 630 (Oak Ridge Road) back to Route 665.

Please note district-wide activities above.

STAUNTON DISTRICT TRAFFIC ALERT

FOR FEBRUARY 19 – 23, 2024

Highway Work Zones in the VDOT Staunton District

STAUNTON – The following is a list of highway work that may affect traffic in the Staunton transportation district during the coming weeks. The Staunton District consists of 11 counties from the Alleghany Highlands to the northern Shenandoah Valley: Alleghany, Bath, Rockbridge, Highland, Augusta, Rockingham, Page, Shenandoah, Frederick, Clarke and Warren.

Scheduled work is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. When traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.

*NEW* or *UPDATE* indicates a new or revised entry since last week’s report.

ALLEGHANY COUNTY

INTERSTATE 64

Mile marker 1 to 41, eastbound and westbound – Alternating lane closures for guardrail improvements, 5 a.m. to 8 p.m. weekdays through April 1.

Mile marker 29 to 30, eastbound – Alternating lane closures for repairs to bridge over Route 42, 7 a.m. to 7 p.m. through March 1.

PRIMARY ROADS

*NEW* Route 220 (Route 220 Highway/Market Avenue) – Flagger traffic control between Route 1706 (Commerce Avenue) and Business Route 60 (Grafton Street) on-ramp for inspection of bridges over Buckingham Branch Railway, CSX Railway and Jackson River, 8:30 a.m. to 4:30 p.m. Tuesday and Thursday.

Various roads – Flagger traffic control for tree and debris removal, drainage work, pothole patching, brush cutting, ditching and shoulder repairs, 7:30 a.m. to 3 p.m. on weekdays.

SECONDARY ROADS

*NEW* Route 619 (Hayes Gap Road) – Flagger traffic control between Route 616 (Rich Patch Road) and Route 657 (Pitzer Ridge Road) for brush removal, 8 a.m. to 2:30 p.m. Tuesday through Friday.

Various roads – Flagger traffic control for ditch work, pipe replacement and brush cutting, 7:30 a.m. to 3 p.m. on weekdays.

BATH COUNTY

PRIMARY ROADS

Various roads – Flagger traffic control for shoulder repairs and pipe cleaning, 7:30 a.m. to 3 p.m. on weekdays.

SECONDARY ROADS

Various roads – Flagger traffic control for brush cutting and pipe cleaning, 7:30 a.m. to 3 p.m. on weekdays.

ROCKBRIDGE COUNTY

INTERSTATE 64

*UPDATE* Mile marker 50 to 55, eastbound – Right shoulder closures for brush removal, 7 a.m. to 5 p.m. Tuesday through Friday.

INTERSTATE 81

*UPDATE* Mile marker 188 to 180, southbound – Right shoulder closures for debris pickup, 7 a.m. to 5 p.m. Wednesday and Thursday.

PRIMARY ROADS

Various roads – Flagger traffic control for pipe replacement, ditch work, tree removal, shoulder repairs, pavement patching and brush cutting. Mobile lane closures for mowing, 7:30 to 3 p.m. on weekdays.

SECONDARY ROADS

Various roads – Flagger traffic control for grading, pipe replacement, ditch work, tree removal, pavement patching, shoulder repairs and brush cutting. Mobile lane closures for mowing, 7:30 a.m. to 3 p.m. on weekdays.

HIGHLAND COUNTY

PRIMARY ROADS

Various roads – Flagger traffic control for pothole patching, brush cutting and shoulder repairs, 7:30 a.m. to 3 p.m. on weekdays.

SECONDARY ROADS

Various roads – Flagger traffic control for brush cutting, pipe cleaning, tree removal, adding stone to unpaved roads and ditch work, 7:30 a.m. to 3 p.m. on weekdays.

AUGUSTA COUNTY

INTERSTATE 64

No lane closures reported.

INTERSTATE 81

*NEW* Mile marker 212 to 214, northbound – Overnight alternating lane closures for maintenance to bridge over Route 11 (Lee-Jackson Highway), 8 p.m. to 7 a.m. Wednesday night.

*UPDATE* Mile marker 221 to 227, northbound and southbound – Overnight southbound left lane closures for moving equipment, 8 p.m. to 6 a.m. Monday through Friday nights. Daytime shoulder closures for tree removal and maintenance operations, 6:30 a.m. to 5:30 p.m. February 19 – March 14. Work is related to I-81 widening project.

*NEW* Mile marker 236 to 235, southbound – Left shoulder closures for tree removal operations in the median, 7:30 a.m. to 4:30 p.m. Monday to Friday.

PRIMARY ROADS

*NEW* Route 11 (Lee Highway) – Northbound right lane closures between Route 940 (Dick Huff Lane) and Staunton city limits for sidewalk installation, 7 a.m. to 5:30 p.m. through May 24.

Route 262 (Woodrow Wilson Parkway) – Eastbound and westbound left shoulder closures due to widening project in the area of the Route 252 (Middlebrook Avenue) interchange, 7:30 a.m. to 4:30 a.m. through April 30.

Route 256 (Weyers Cave Road) – Flagger traffic control near Rockingham line for maintenance to bridge over South River, 7 a.m. to 7 p.m. through Friday.

SECONDARY ROADS

Route 624 (South Delphine Avenue, Waynesboro) – Shoulder closures between South Oak Lane and Chinquapin Drive for work related to construction of Waynesboro Southern Corridor, through May 30, 2025.

Route 635 (Barterbrook Road) – Closed between I-81 frontage roads (FR-217 and FR-218) for bridge replacement as part of I-81 southbound auxiliary lane project. Follow posted detour. Expected completion summer 2025.

*NEW* Route 640 (Old White Bridge Road) – Flagger traffic control between Route 250 (Jefferson Highway) and Route 254 (Hermitage Road) for inspection of bridge over CSX Railway, 8:30 a.m. to 4:30 p.m. Friday.

Route 664 (Mount Torrey Road) – Shoulder closures and occasional flagger traffic control between Route 624 (Lyndhurst Road) and Route 894 (Mount Torrey Road) for water line installation, 7 a.m. to 5 p.m. through March 29. Estimated completion summer 2024.

Route 664 (Lyndhurst Road, Waynesboro) – Shoulder closures between Miami Avenue and Purdue Street for work related to construction of Waynesboro Southern Corridor, through June 30, 2025.

*NEW* Route 675 (Broadhead School Road) – Flagger traffic control between Route 11 (Lee-Jackson Highway) and Route 604 (McClures Mill Road) for utility work, 9 a.m. to 2:30 p.m. February 19 – February 29.

*NEW* Route 778 (Knightly Mill Road) – Middle River bridge closed beginning Wednesday, February 28. Traffic can use nearby Route 774 (Cline River Road) bridge.

*NEW* Route 795 (Entry School Road) – Flagger traffic control between Route 608 (Long Meadow Road) and Route 640 (Old White Bridge Road) for utility work, 9 a.m. to 2:30 p.m. February 19 – February 29.

*NEW* Route 796 (Kiddsville Road) – Flagger traffic control between Route 797 (Miller Road) and Route 608 (Long Meadow Road) for utility work, 9 a.m. to 2:30 p.m. February 19 – February 29.

Various roads – Mobile traffic control for mowing operations. Flagger traffic control for drainage work, tree removal, shoulder repairs, pavement patching and brush cutting, 7:30 to 3 p.m. on weekdays.

ROCKINGHAM COUNTY

INTERSTATE 81

Mile marker 242 to 248, northbound and southbound – Overnight alternating lane closures, 8 p.m. to 7 a.m. through December 2026. Overnight slow-roll traffic control as needed from 11 p.m. to 5 a.m. Expect delays. During slow-roll operations, temporary on-ramp closures possible at exits 243, 245 and 247. Traffic restrictions are related to Route 33 bridge and interchange project.

*NEW* Mile marker 246 to 248, northbound – Right shoulder closures for sign work, 8 a.m. to 5 p.m. Monday through Friday.

PRIMARY ROADS

Route 33 (Rawley Pike) – Flagger and pilot-truck traffic control between Dry Run Road and Switzer Lake Road for road widening project, 7:30 a.m. to 5 p.m. through April 5.

Route 33 (East Market Street, Harrisonburg) – 24/7 shoulder closures and traffic lane shifts between Vine Street/Hawkins Street and University Boulevard for bridge and roadway work. Single lane closures as needed. Work zone speed limit 25 miles an hour with automated speed enforcement. Traffic restrictions are for Route 33 bridge replacements and interchange improvement with expected project completion in fall of 2026.

Route 33 (Spotswood Trail) – Eastbound and westbound alternating lane closures near Elkton town limits for maintenance to bridges over Route 340, 7 a.m. to 7 p.m. through March 1.

Route 253 (Port Republic Road) – Flagger traffic control between Route 605 (Main Street, Port Republic) and Route 1601 (New Haven Road) for maintenance to bridge over North River, 7 a.m. to 7 p.m. through March 1.

Route 256 (Third Street, Grottoes) – Flagger traffic control near Augusta County line for maintenance to bridge over South River, 7 a.m. to 7 p.m. through Friday.

Route 340 (East Side Highway) – Northbound and southbound alternating lane closures near Elkton southern town limits for maintenance to Route 33 overpass bridges, 7 a.m. to 7 p.m. through March 1.

Various roads – Mobile traffic control for mowing operations. Flagger traffic control for pipe replacement, ditch work, tree removal, shoulder repairs, pavement patching and brush cutting, 7:30 a.m. to 3 p.m. on weekdays.

SECONDARY ROADS

No lane closures reported.

PAGE COUNTY

PRIMARY ROADS

Various roads – Mobile traffic control for mowing operations. Flagger traffic control for pipe replacement, ditch work, tree removal, shoulder repairs, pavement patching and brush cutting, 7:30 a.m. to 3 p.m. on weekdays.

SECONDARY ROADS

Various roads – Flagger traffic control for brush cutting and pipe cleaning, 7:30 a.m. to 3 p.m. on weekdays.

SHENANDOAH COUNTY

INTERSTATE 81

*NEW* Mile marker 296, southbound – Right shoulder closures for brush removal operations, 8:30 a.m. to 3 p.m. Tuesday through Friday.

*NEW* Mile marker 296 to 299, northbound – Right shoulder closures for utility work, 8 a.m. to 4 p.m. Monday through Friday.

PRIMARY ROADS

No lane closures reported.

SECONDARY ROADS

Route 620 (Smith Creek Road) – Flagger traffic control between Route 826 (Woods Chapel Road) and Route 732 (Cardinal Road) for bridge work over tributary to Smith Creek, 6 a.m. to 7 p.m. through March 3.

Route 625 (Harman Road) – Flagger traffic control between Route 642 (Swartz Road) and Route 11 (Old Valley Pike) for maintenance to I-81 overpass bridge, 7 a.m. to 7 p.m. through Friday.

FREDERICK COUNTY

INTERSTATE 81

Mile marker 300 to 301, northbound and southbound – Overnight lane closures and traffic-lane shifts as needed, 8 p.m. to 7 a.m. through March 2024. Shoulder closures 24/7. Work zone speed limit 55 miles an hour. Work is related to southbound acceleration ramp extension and bridge widening with estimated completion in fall 2024.

PRIMARY ROADS

*NEW* Route 11 (Valley Pike) – Northbound right shoulder closures between Route 1129 (Prosperity Drive) and Route 872 (Hood Way) for signal installations, 7 a.m. to 5 p.m. Monday through Thursday.

*NEW* Route 11 (Martinsburg Pike) – Southbound right shoulder closures between I-81 interchange and Crown Lane for signal installations, 7 a.m. to 5 p.m. Monday through Thursday.

*UPDATE* Route 37 – Southbound right shoulder closures between the ramp from Route 622 (Cedar Creek Grade) and Route 642 (Tasker Road) for brush removal, 8:30 a.m. to 3 p.m. Tuesday through Friday.

SECONDARY ROADS

Route 600 (North Hayfield Road)– No lane closures, but utility work happening in right of way between Route 50 (Northwestern Pike) and Route 684 (Gainesboro Road), 8:30 a.m. to 5:30 p.m. through February 29.

*NEW* Route 661 (Redbud Road) – Flagger traffic control between Route 662 (Milburn Road) and Route 660 (Woods Mill Road) for road maintenance, 9 a.m. to 3:30 p.m. February 19 – December 31.

*NEW* Route 662 (Milburn Road) – Flagger traffic control between Route 661 (Redbud Road) and Route 761 (Old Charles Town Road) for road maintenance, 9 a.m. to 3:30 p.m. February 19 – December 31.

CLARKE COUNTY

PRIMARY ROADS

No lane closures reported.

SECONDARY ROADS

No lane closures reported.

WARREN COUNTY

INTERSTATE 66

No lane closures reported.

INTERSTATE 81

*NEW* Mile marker 299 to 300, northbound – Right shoulder closures for utility work, 8 a.m. to 4 p.m. Monday through Friday.

Mile marker 299 to 300, northbound and southbound – Overnight lane closures and traffic-lane shifts as needed, 8 p.m. to 7 a.m. through March 2024. Shoulder closures 24/7. Work zone speed limit 55 miles an hour. Work is related to southbound acceleration ramp extension and bridge widening with estimated completion in fall 2024.

PRIMARY ROADS

No lane closures reported.

SECONDARY ROADS

No lane closures reported.

Vegetation management may take place district wide on various routes. VDOT reminds motorists to use extreme caution when traveling through work zones.

For updated traffic alerts and traveler information, dial 511 or visit 511virginia.org.

The VDOT Customer Service Center can assist with reporting road hazards, asking transportation questions, or getting information related to Virginia’s roads. Call 800-FOR- ROAD (800-367-7623) or use its mobile friendly website at https://my.vdot.virginia.gov. Agents are available 24 hours-a-day, seven days a week.

The VDOT Staunton District is on Facebook and X (Twitter). Follow VDOT statewide accounts on Facebook, X (Twitter), YouTube, Instagram, LinkedIn and Flickr. The VDOT Web page is located at http://www.VirginiaDOT.gov.

 

SCHEDULED CONSTRUCTION AND MAINTENANCE WORK

CULPEPER DISTRICT: Feb. 19-23, 2024

CULPEPER — The following highway work is scheduled, weather permitting, in the Culpeper District during the next week. Traffic movements may be restricted and speed limits reduced in work zones. (NEW) or(UPDATE) indicate revisions since last week’s report.

Culpeper District traffic information is also available on Twitter at @VaDOTCulp and on VDOT’s website at http://www.virginiadot.org/travel/travel_alerts/culpeper/default.asp.

Albemarle County 

(NEW) Other roadside – Expect mobile work zone with right shoulder closures in the following areas:

  • Interstate 64, between mile marker 123 and mile marker 125 in the westbound lanes, Monday, 9 a.m. to noon.
  • Interstate 64, between mile marker 118 and mile marker 119 in the westbound lanes, Monday, 11 a.m. to 2 p.m.

New Roadway Construction – Construction of a roundabout at Route 743 (Hydraulic Road) and Hillsdale Drive. Expect lane and shoulder closures with flaggers in the following areas nightly, Monday through Thursday, 9 p.m. to 6 a.m., 10 p.m. Friday to 9 a.m. Saturday, 9 p.m. Saturday to 10 a.m. Sunday, 8 p.m. Sunday to 6 a.m. Monday, through May 5.

  • Route 743 (Hydraulic Road), between U.S. 29 (Emmet Street North) and Brandywine Drive, nightly in the northbound and southbound lanes.
  • Route 743 (Hydraulic Road), between U.S. 29 (Emmet Street North) and Cedar Hill Road in the northbound and southbound lanes.

Tree removal – Expect alternating lane closures with flaggers, daily, 7:30 a.m. to 4 p.m. in the following areas:

  • Route 20 (Scottsville Road), between Route 53 (Thomas Jefferson Parkway) and Route 726 (James River Road) in the northbound and southbound lanes.
  • Route 53 (Thomas Jefferson Parkway), between Route 729 (Buck Island Road) and Route 732 (Milton Road) in the eastbound and westbound lanes.

Utility work under VDOT permit – Expect lane and shoulder closures in the following areas:

  • U.S. 29 (Monacan Trail), intermittent slow roll closures with flaggers between Route 692 (Plank Road) and Route 708 (Red Hill Road) in the northbound and southbound lanes, daily, 9 a.m. to 3 p.m.
  • U.S. 29 (Monacan Trail), intermittent slow roll closures with flaggers between Route 633 (Cove Garden Road) and Route 760 (Red Hill School Road) in the northbound and southbound lanes, daily, 9 a.m. to 3 p.m.

(NEW) Interstate 64 – Pothole patching. Expect mobile, alternating lane closures between mile marker 100 and mile marker 131 in the eastbound and westbound lanes Wednesday and Thursday, 8 a.m. to 3:30 p.m.

(NEW) U.S. 29 (29 Bypass Expressway) – Equipment installation. Expect slow roll operation between U.S. 29 Business (Fontaine Avenue Extended) and the ramp from U.S. 29/U.S. 250 in the northbound and southbound lanes, from 10 p.m. Wednesday to 6 a.m. Thursday.

U.S. 250 (Rockfish Gap Turnpike) – Road widening project. Expect lane closures between Birdsall Lane and Route 750 (Old Turnpike Road). The westbound lanes will remain reduced from two lanes to one and the eastbound lane shift will remain in place. This is a long-term closure for the duration of the project. Expected completion date, April 2024.

Route 20 (Scottsville Road) – Bridge superstructure repairs/replacement. Expect temporary traffic signal with new traffic pattern at Route 708 (Red Hill Road). Route 708 is narrowed to one lane for construction on the bridge over the North Fork Hardware River in the southbound lanes. Project completion date, Dec. 2024.

(NEW) Route 6 (Irish Road) – Shoulder repairs. Expect mobile, alternating lane closures between Route 627 (Porters Road) and Route 715 (Chestnut Grove Road) in the eastbound and westbound lanes, Tuesday, 8 a.m. to noon.

(UPDATE) Route 20 (Stony Point Road) – Tree trimming. Expect mobile, alternating lane closures between Route 1421 (Elk Drive) and the Orange County line in the northbound and southbound lanes, Tuesday through Friday, 9 a.m. to 2 p.m.

Route 641 (Frays Mill Road) – Other bridge work. Road closed at Route 743 (Advance Mills Road) for replacement of bridge over Marsh Run. Drivers on U.S. 29 (Seminole Trail) who need to access Route 743 north and west of the closure should use Route 607 (Cedar Grove Road). Expected completion date, Dec. 5, 2024.

(NEW) Utility work under VDOT permit – Expect lane closures with directional signs at the following roundabouts, daily, 7 a.m. to 5 p.m.:

  • Route 1403 (Berkmar Drive) at Towncenter Drive.
  • Route 1403 (Meeting Street) at Timberwood Boulevard.

City of Charlottesville

(NEW) U.S. 250 (Bypass Expressway) – Roadway improvements. Expect lane and shoulder closures with flaggers between U.S. 29 (Emmet Street North) and Route 3412 (Dairy Road) in the eastbound and westbound lanes nightly, Monday through Thursday, 9 p.m. to 6 a.m., 10 p.m. Friday to 9 a.m. Saturday, 9 p.m. Saturday to 10 a.m. Sunday, 8 p.m. Sunday to 6 a.m. Monday, nightly through April 19.

Culpeper County

(NEW) Utility work under VDOT permit – Expect lane and shoulder closures in the following areas:

  • U.S. 29 (James Madison Highway North) mobile work zone with rolling stops at Route 651 (Freemans Ford Road) in the northbound and southbound lanes, Tuesday and Wednesday, 10 a.m. to noon.
  • Route 669 (Carrico Mills Road), occasional shoulder and lane closures between Route 3 (Germanna Highway) and Route 672 (Stones Mill Road) in the northbound and southbound lanes, daily, 9 a.m. to 3 p.m.
  • Route 672 (Stones Mill Road), alternating lane closures between Route 669 (Carrico Mills Road) and Route 724 (Youngs Lane) in the eastbound and westbound lanes, daily, 9 a.m. to 3 p.m.

(NEW) U.S. 522 (Sperryvile Pike) – Other construction. Expect alternating lane closures between North Blue Ridge Avenue and Virginia Avenue in the northbound and southbound lanes, daily through Friday, 9 a.m. to 3 p.m.

(UPDATE) Route 229 (Rixeyville Road) – Road widening project. Expect alternating lane closures between U.S. 211 (Lee Highway) and Route 694 (Ira Hoffman Lane) in the northbound and southbound lanes, daily, 7:30 a.m. to 5:30 p.m.

Fauquier County

(UPDATE) Utility work under VDOT permit – Expect lane and shoulder closures in the following: areas:

  • Route 55 (John Marshall Highway), mobile alternating lane closures between Route 622 (Whiting Road) and Route 709 (Belvoir Road) in the eastbound and westbound lanes, daily, 9 a.m. to 3 p.m.
  • Route 651 (Freemans Ford Road), mobile, alternating lane closures between Route 658 (Cemetery Road) and Route 769 (Beales Branch Lane) in the northbound and southbound lanes, Monday, 9 a.m. to 3:30 p.m.
  • Route 676 (Riley Road), alternating lane closures between Brookside Parkway and Route 605 (Dumfries Road) in the southbound lanes, 9 a.m. to 3:30 p.m.
  • Route 690 (Bear Wallow Road), alternating lane closures between Filly Lane and the Warrenton Town line in the northbound and southbound lanes, 9 a.m. to 3 p.m.

(NEW) Interstate 66 – Brush removal. Expect both shoulders closed between mile marker 16 and mile marker 34 in the eastbound and westbound lanes, Tuesday through Friday, 7 a.m. to 3:30 p.m.

(NEW) U.S. 15 (Eastern Bypass North) – Bridge inspection. Expect alternating lane closures at the Warrenton Town line in the northbound and southbound lanes, Thursday, 8 a.m. to 5 p.m.

(NEW) Route 672 (Blackwell Road) – Pipe repairs/installation. Road closed between Route 1460 (Ivy Hill Drive) and Route 605 (Arlie Road) in the southbound lanes, daily, starting Tuesday, 8 a.m. to 4:30 p.m. through March 1.

Greene County

(UPDATE) Route 230 (Madison Road) – Road widening project. Expect alternating lane closures between Route 637 (Octonia Road) and the Madison County line in the eastbound and westbound lanes, daily through Tuesday, 7:30 a.m. to 5:30 p.m.

Louisa County

Construction of new roundabout – Expect alternating lane closures daily, 7 a.m. to 6 p.m. in the following areas. Project anticipated completion date, Jan. 31, 2025.

  • U.S. 522 (Zachary Taylor Highway) between Route 623 (Chopping Road) 0.3 miles north of Route 208 (New Bridge Road) in the northbound and southbound lanes.
  • Route 208 (New Bridge Road) between U.S. 522 (Zachary Taylor Highway) and Alma Gaynelle Drive in the eastbound and westbound lanes.

(NEW) Utility work under VDOT permit – Expect lane and shoulder closures in the following areas:

  • Route 652 (Kentucky Springs Road), right shoulder closure between Route 208 (New Bridge Road) and Route 614 (Carrs Bridge Road) in the northbound lanes, daily, 9 a.m. to 3 p.m.
  • Route 652 (Kentucky Springs Road), right shoulder closure between Route 652 (Pine Point Place) and Route 700 (Haley Drive) in the southbound lanes, daily, 8 a.m. to 4:30 p.m.
  • Route 679 (Firehouse Drive), lane and shoulder closures between Route 692 (Hickory Creek Road) and Poplar Drive in the northbound and southbound lanes, Tuesday, 9 a.m. to 3 p.m.
  • Route 700 (Haley Drive), right shoulder closure between Route 652 (Kentucky Springs Road) and dead end of Route 700 (Haley Drive in the northbound lanes, daily, 8 a.m. to 5 p.m.

(NEW) Interstate 64 – Pothole patching. Expect mobile, alternating lane closure between mile marker 131 and mile marker 147 in the eastbound and westbound lanes, Wednesday and Thursday, 8 a.m. to 3:30 p.m.

(NEW) Interstate 64 – Ditch cleaning. Expect both shoulders closed between mile marker 131 and mile marker 147 in the eastbound and westbound lanes, Monday through Friday, 8 a.m. to 3:30 p.m.

(NEW) U.S. 15 (James Madison Highway – Super load. Expect slow-moving vehicle in mobile work zone between U.S. 250 (3 Notch Road) and Interstate 64 in the northbound and southbound lanes, nightly, Friday through Monday, Feb. 27, 9 p.m. to 5:30 a.m.

Route 661 (Crewsville Road) – Pipe repairs/installation. Road closed between Route 601 (Paynes Mill Road) and Route 602 (Copper Line Road), daily through Feb. 29, 2024.

Madison County

U.S. 29 (South Seminole Trail) – Bridge repairs. Expect alternating lane closures between Route 621 (Seville Road) and Route 609 (Fredericksburg Road) in the southbound lanes, daily, 7 a.m. to 5 p.m.

(NEW) Utility work under VDOT permit – expect alternating lane closures in the following areas, Monday through Friday, 9 a.m. to 3 p.m.:

  • Route 621 (Seville Road), between Route 662 (Shelby Road) and Route 1030 (Oaks Lane) in the eastbound and westbound lanes.
  • Route 662 (Shelby Road), between Route 621 (Seville Road) and U.S. 29 (South Seminole Trail) in the southbound lanes.

Rappahannock County

U.S. 211 (Lee Highway) – Pipe repairs/installation. Expect alternating lane closures between Route 640 (Battle Mountain Road) and Route 611 (Seven Ponds Road) in the eastbound and westbound lanes, daily, 8 a.m. to 5 p.m.

Route 729 (Richmond Road) – Bridge approach repairs. Expect flagging operation at Route 676 (Gore Road) in the northbound lanes, daily, 7 a.m. to 5 p.m.

Road conditions and other real-time travel information can be found on the511 Virginia website,

the free VDOT 511 mobile app or by calling 511 from any phone in Virginia. VDOT updates are also on the Culpeper District Facebook page and the district’s Twitter account, @VaDOTCulp.

(END)

VDOT’s nine-county Culpeper District includes the counties of Albemarle, Culpeper, Fauquier, Fluvanna, Greene, Louisa, Madison, Orange and Rappahannock. The independent city of Charlottesville maintains its own roads.

LEAVE A REPLY

Please enter your comment!
Please enter your name here